Upcoming projects
Construction of Port 2000 berths 11 and 12
Finalisation of Port 2000 phase 3 involves creating quay berths 11 and 12 and signing a concession agreement for them. This will help enhance port operations for the main maritime alliances. It is a unique project for France and will provide a new seagoing container terminal located at the mouth of the Seine with connections out to the World.
Key figures:
- Area: 42 hectares; 700m additional quay span
- Cost: €154.5m
- Delivery: 2024
Improved river access for Port 2000
A construction project involving the provision of a channel (known locally as the “cat flap”) providing direct access to Port 2000 for all types of river vessel.
Key figures:
- Cost: €125m
- Delivery: 2024
To find out more, go to: https://accesfluvialport2000.haropaport.com/fr
A welcome for offshore wind turbines
A project for the provision of land, port facilities and ship access enabling Siemens Gamesa’s factory to be set up for the manufacture of wind turbine blades and nacelles. Plant output will serve the offshore windfarms installed in the English Channel/North Sea.
Work undertaken by the port:
- Land preparation for construction
- Construction of two berths spanning 400m of quayside
Key figures:
- Area: 36 hectares
- Cost: €146.7m
- Delivery: 2023